Cox arena-ARC Remodel

 

Cox Arena and ARC Remodel

Construction Project

Project Summary

Cost: $1,700,000
Status: Complete
Funding: Operations Revenue
Completion Date: November 2002

Project Contacts

Executive Architect: Mosher, Drew, Watson, & Ferguson
Design-Build Contractor: Sea-Pac Engineering
Project Manager: Michael Woomer

Project Description

Basketball program offices previously in Cox Arena were relocated to the new Aztec Athletics Center with other athletics programs. This project converted the vacated space into an improved hospitality center serving the mezzanine level. It also added a concession stand at the arena floor level and handicapped accessible toilet facilities.

Aztec Recreation Center (ARC)

The success of Aztec Recreation Center (ARC) created the need for expanded administrative offices, enlarged membership services desk, an improved entrance lobby and modernized laundry facilities. This remodel provides these improvements and enhances the Aztec Recreation Center.

 